cancel
Showing results for 
Search instead for 
Did you mean: 

Resource in Work Package

former_member114268
Participant
0 Kudos

Hello Team,

I am not able to add resource for Work Package for internal / Customer Project.

Kindly guide me how can i add resource in Work Package.

Thanks & Regards.

Accepted Solutions (1)

Accepted Solutions (1)

NikolaiE
Advisor
Advisor
0 Kudos

Hello,

please follow the steps in test script "Customer Project Management - Project-Based Services (Scope Item J11) and

Internal Project Management - Project-Based Services (1A8).

Scope Item Customer Project J11:

https://rapid.sap.com/bp/#/browse/scopeitems/J11

Chapters:

4.4 Maintain Work Package Staffing (p. 26)

4.5 Maintain Work Package Staffing (Without Scope Item 1KC-Advanced Resource Management- Project-Based Services) (p. 30)

4.6 Maintain Work Package Staffing (With Scope Item 1KC-Advanced Resource Management- Project-Based Services) (p. 33)

Scope Item Internal Project 1A8:

https://rapid.sap.com/bp/#/browse/scopeitems/1A8

Chapters:

4.5 Maintain Work Package Staffing (Without Scope Item 1KC - Advanced Resource Management - Project-Based Services) (p. 25)

4.6 Maintain Work Package Staffing (With Scope Item 1KC - Advanced Resource Management - Project-Based Services) (p. 28)

4.7 Maintain Work Package Staffing (p. 31)

These scope items manage the complete end-to-end process of selling and performing project-based services to customers and inside the company.

Best regards,

Nikolai Emling

Answers (0)