Internal Project Settlement

0 Kudos

Hello,

I need to understand, How is the settlement run for internal project take place?

Like what is the cost that is going to settlement after maintaining settlement Rule.

Thanks & Regards,

Accepted Solutions (1)

Accepted Solutions (1)

NikolaiE
Advisor
Advisor
0 Kudos

Hello Mayur,

costs are collected in projects only temporarily. They are settled to one or more receivers as part of period-end processing. The test script for scope item 1A8 (and 1NT) shows you how to maintain settlement rules at work-package level, how to run settlement and how to analyze the the internal project KPIs.

1A8: https://rapid.sap.com/bp/#/browse/scopeitems/1A8

1NT: https://rapid.sap.com/bp/#/browse/scopeitems/1NT

Best regards,

Nikolai

Answers (2)

Answers (2)

0 Kudos

Hello Riwa / Nikolai,

Thank you for the inputs,

Have run the process for settlement and have successfully done settlement run for internal project.

Thanks & Regards.

riwamouawad
Advisor
Advisor
0 Kudos

Hi Mayur,

Just like nikolai.emling mentioned below, the test script for internal projects is 1NT - Project Financial Control. One point I wanted to add was that there are 3 different settlement receivers: Cost Centers, G/L Accounts, and Fixed Assets.