on 05-30-2019 7:07 AM
When scheduling a job in "Detect MRP Situations" the job fails and error "An error occurred. Please create an incident on component PP-FIO" occurs.
Please take a look at note 2733550 - MRP Material Situations Handling ( https://launchpad.support.sap.com/#/notes/2733550 ).
According to the note, for calculation of the MRP - Situations, the API Material Planning Data - Read is used. The number of objects to be read by this service is not restricted by the system. If too many materials meet your selected properties, the system can cancel the processing due to memory overload. This also applies to the background job PPH_MRP_SITUATIONS_CREATE and shall, therefore, be considered when setting the parameters for selection.
Best regards,
Mateus.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here are some SAP resources you may review based on your topic "component,component,mrp,scheduling a job,mrp,app,create,create"
SAP GoingLive Check
The session is scheduled a minimum four weeks before your start of production ... The service sessions are used to analyze the important components of your systems. ... the number of users for each application, the expected data volume and the ... Step-by-step optimization of central background processing (MRP run, ?...
https://support.sap.com/en/offerings-programs/support-services/goinglive-check.html
SAP Fiori Apps Library
SAP Fiori lighthouse apps. Actual Cash Flow ... Approve Closing Tasks. Approve Master Data - ... Create Optimal Orders for Shipment. Custom Business Objects.
https://fioriappslibrary.hana.ondemand.com/sap/fix/externalViewer/#/home
SAP Globalization Services
Find below all the information needed for your country to help you in the rollout of your SAP ERP application (SAP ERP and S/4 HANA). Keep your core finance?...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here are some SAP resources you may review based on your topic "component,component,mrp,scheduling a job,mrp,app,create,create"
SAP GoingLive Check
The session is scheduled a minimum four weeks before your start of production ... The service sessions are used to analyze the important components of your systems. ... the number of users for each application, the expected data volume and the ... Step-by-step optimization of central background processing (MRP run, ?...
https://support.sap.com/en/offerings-programs/support-services/goinglive-check.html
SAP Fiori Apps Library
SAP Fiori lighthouse apps. Actual Cash Flow ... Approve Closing Tasks. Approve Master Data - ... Create Optimal Orders for Shipment. Custom Business Objects.
https://fioriappslibrary.hana.ondemand.com/sap/fix/externalViewer/#/home
SAP Globalization Services
Find below all the information needed for your country to help you in the rollout of your SAP ERP application (SAP ERP and S/4 HANA). Keep your core finance?...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.