Hello, Experts,
I want to check how does the sys calculate the overdue in APP : Manage Work Center Capacity.
For example,in below screen, the overdue = 51.84
I think this is calculated based on the prod order list in below screen:
I calculate in excel as below:
I calculate result is 64.37, different with sys result 51.84
Would you please help to check the reason ?
Thanks a lot
RGDS
Joanna Qiu
Hi Joanna,
The overdue is the sum of the number of hours that will be needed for the completion of overdue orders and operations from the selected evaluation horizon in the past.
For example, if the selected evaluation horizon is 7 days, overdue orders and operations till up to 7 days in the past from the current date are considered. In addition, the calculation includes the number of hours leftover from partially confirmed operations.
Thanks and regards,
Mateus.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.