Task not appearing on Manage My Timesheet inspite of assigning resource on Work Package

Former Member
0 Kudos

Hello,

I have assigned the myself as resource on a work package but when I go to Manage My Time sheet app, I cannot see any tasks or work package in my list. This is same with all id I assigned couple of resources and went to individual id to see if the work packages reflect on manage my time sheet app.

Can anyone tell me if there is any missing configuration of master data in system for the same. I have assigned resource to activity id and have maintained resource as employee in business partner as well.

Regards,

Nitesh Panchal

Accepted Solutions (1)

Accepted Solutions (1)

ana_goncalves
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Nitesh,

In what stage is the project currently? If the project is In Execution, did you confirm the resource? See screenshot attached.

Kind regards,

Ana

Former Member
0 Kudos

Thanks Ana, it worked