on 12-30-2018 1:43 AM
Dear Community,
I need your help.
Is there any way to enter financial plan data for the project in the S/4 HANA Cloud Solution without using the app "Import financial plan data" ? May be manually ?
Thanks in advance for your help.
Regards,
Silvère
Hi Oulsil,
No - the only way to enter financial plan data is through the "Import Financial Plan Data" application.
Best,
Riwa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't believe there is (I certainly haven't found one anyway) - I think the assumption with S4HC is that planning is done elsewhere and merely loaded to support comparative reporting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I agree with Clare, based on everything I've seen or experienced with projects there is no way to separate app to enter plan or budget data. You can record baseline expenses in the project services centric projects which is a nice feature I wish they would bring over since not all projects are directly related to a financial plan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.