Hi everyone,

Can planned orders be deleted?

Thank you,

Markus

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Markus,

Planned orders can be deleted in the following ways:

1.) Delete Multiple Planned orders manually using App Monitor Production/Planned Orders - In the sys status select the status of planned orders.

a list of all planned orders will be displayed.

Select the planned orders you would like to delete using the control key.

Select delete for each planned order.

2.) You can rerun MRP with regenerative planning mode 3.

Let me know if you have any questions.

Thanks

Shashi

Answers (4)

Answers (4)

AKK
Explorer
0 Kudos

You can also delete Planned Order manually.

Open relevant Planned Order and press delete button.

AKK
Explorer
0 Kudos

Yes, you can also delete Planned Order manually.

Open relevant Planned Order and press delete button.

Devin_Good
Advisor
Advisor
0 Kudos

Hi Markus,

In the application "schedule mrp runs" if you create a new run, navigate to the "parameters section," chose "planning mode" 3 which is delete and recreate planning data. This will delete current planned orders and recreate based on the the most up to date requirements.

Does this make sense?

Devin

Devin_Good
Advisor
Advisor
0 Kudos

Hi Markus,

Yes, you can rerun mrp with regenerative planning chosen.

Hope that helps,

Devin

mberends
Explorer
0 Kudos

Hi Devin,

Thank you for your answer. Could you please describe some more detailed steps.

Best,

Markus

Gabor_Kovacs
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Markus,

Could you confirm that the MRP runs with the settings Devin mentioned worked, please?

Alternatively you can use app Change Planned Order - select the order, click on the change (pencil icon), then on the bottom-right of the screen you can see the Delete option.

The most elegant option is using the Monitor Material Coverage app - find your product, go to the details (Manage Materials). Find the Planned order and select Delete from the Actions drop down.

mberends
Explorer
0 Kudos

gabor.kovacs2

Hi Gabor,

Devin's solution unfortunately didn't work. We will try your suggestion now. I will give you a feedback.

Thank you,

Markus

former_member132363
Active Contributor
0 Kudos

Hi Markus - I would like to follow up to make sure the solution suggested worked for you. Can you please "Mark Best Answer" on Sashi or Devin replies that provided you with the best solution so we can close out this question.